March 31, 2013: LAST DATE USEFUL FOR THE ADAPTATION OF PLANTS IN MEDIUM VOLTAGE

Mar 05, 2013
The deliberation of the Authority for Electricity and Gas num. 84/2012/R/EEL, Art. 5 (subsequently amended by AEEG resolution 165/2012/R/EEL) requires owners to retrofit a power installations exceeding 50kW connected in Medium Voltage and came into operation no later than 31/03/2012, in order to ensure compliance with the requirements laid down in 'Annex A70 of the Network Code issued by Terna.

For more information please see the link below:
COMUNICATO ANIE 13 FEBBRAIO 2013
DELIBERAZIONE 8 MARZO 2012 - 84/2012/R/EEL
DELIBERAZIONE 26 APRILE 2012 - 165/2012/R/EEL
Allegato A. 70


If they are not adapted their facilities according to the schedule and the manner prescribed by resolution 84/2012/R/eel, will be notified to the producer and to the Manager of Energy Services SpA - GSE that will suspend the incentives until full adaptation of plants.
The retrofit must be made no later than 31/03/2013, and is paid by the Authority for Electricity and Gas with a prize worth up to € 5,000.00, the amount of which lesses with the passage of time, as shown in AEEG 165/2012/R/EEL.

Please remember that protection systems Lovato Electric (PMVF 30) already comply with the third edition of the CEI 0-16, therefore valid immediately and also for plants whose requests for connections are made after March 31.