ENPHASE ENERGY INFORMATION - USE FROM 1st July 2012

Jun 06, 2012
Following the resolution of March 8, the Authority for Electricity and Gas (AEEG) has issued a new resolution 84/12, which introduces two regulations, CEI 0-21 and Annex A.70 the network code Terna, relating to the security of the national electricity system.

The New Regulations introduce, starting from July 1, important changes that require updating of conversion devices. Enphase's providing the changes required to make the system a microinverter to comply with the new standards mentioned above.
There are two actions: a software update and the installation of an external device for the control of reactive power.

Please download the attached file below that explains in detail what are the changes that will be made to Enphase Energy microinverter.